| SR 303 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | SHALERSVILLE TWP | PRESERVATION | $1,447,400 | 25236 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $1,158,400 $289,000 | 2012 2012 | ODOT |
| Description: BRIDGE DECK & SUPERSTRUCTURE REPLACEMENT AND SUB-STRUCTURE REPAIRS OVER CUYAHOGA RIVER | ||||
| IR 76 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | BRIMFIELD TWP,ROOTSTOWN TWP | PRESERVATION | $9,220,000 | 76348 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| IM STATE | CONST CONST | $8,298,000 $922,000 | 2013 2013 | ODOT |
| Description: MINOR REHABILITATION AND RESURFACING FROM .21 MILES EAST OF TALLMADGE RD TO .23 MILES WEST OF NEW MILFORD RD | ||||
| SR 14 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | RAVENNA TWP | OPERATIONAL | $7,559,400 | 78278 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP STATE STATE HSP STATE | PE PE PE RW RW RW CONST C | $450,000 $804,400 $50,000 $360,000 $40,000 $455,000 $3,000,000 $405,000 $795,000 | 2013 2012 2013 2013 2013 2013 2015 2015 2015 | ODOT |
| Description: INTERSECTION IMPROVEMENTS, ELIMINATE NEWTON FALLS LEG, EXTEND PECK RD TO SR 59 | ||||
| PROSPECT ST,CR 74 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | RAVENNA TWP | OPERATIONAL | $1,684,000 | 79009 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL HSP LOCAL HSP | ENG ENG RW RW CONST CONST | $43,500 $4,800 $90,000 $10,000 $1,215,000 $235,000 | 2012 2012 2012 2012 2013 2013 | PORTAGE COUNTY ENGINEER |
| Description: TURN LANES AND SIGNALS FROM SUMMIT RD TO HAYES RD | ||||
| SR 44,SR 88 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | MANTUA TWP,GARRETTSVILLE | PRESERVATION | $2,015,000 | 81573 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $1,612,000 $403,000 | 2012 2012 | ODOT |
| Description: RESURFACING, BRIDGE WORK, CULVERT WORK FROM SR 82 TO GEAUGA COUNTY LINE, FROM LIBERTY ST TO GEAUGA CO LINE | ||||
| IR 76 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | ROOTSTOWN TWP,EDINBURG TWP,HIRAM,GARRETTSVILLE | PRESERVATION | $4,950,000 | 81636 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| IM STATE | CONST CONST | $4,455,000 $495,000 | 2015 2015 | ODOT |
| Description: RESURFACING AND MISCELLANEOUS BRIDGE WORK FROM .14 MILES WEST OF NEW MILFORD RD TO .07 MILES WEST OF ROCK SPRING RD | ||||
| HOPKINS RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | NELSON TWP | PRESERVATION | $675,000 | 82330 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR-C LOCAL | CONST CONST | $540,000 $135,000 | 2012 2012 | PORTAGE COUNTY ENGINEER |
| Description: BRIDGE REPLACEMENT OVER EAGLE CREEK | ||||
| SR 14 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | STREETSBORO | PRESERVATION | $1,160,000 | 82907 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| NHS STATE | CONST CONST | $928,000 $232,000 | 2013 2013 | ODOT |
| Description: RESURFACING WORK ON TWO BRIDGES | ||||
| SR 44 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | SHALERSVILLE TWP,MANTUA | PRESERVATION | $942,100 | 82913 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STATE STP-S STATE | PE CONST CONST | $47,500 $704,000 $176,000 | 2012 2014 2014 | ODOT |
| Description: MINOR REHABILITATION AND BRIDGE WORK FROM SR 303 TO NORTH OF MILL ST | ||||
| SR 14 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | RAVENNA TWP, EDINBURG TWP | PRESERVATION | $2,385,000 | 82916 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $1,908,000 $477,000 | 2014 2014 | ODOT |
| Description: MINOR REHABILITATION, BRIDGE WORK FROM RAVENNA EAST CORP LINE TO TALLMADGE RD | ||||
| US 224 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | SUFFIELD TWP,RANDOLPH TWP,ATWATER TWP | PRESERVATION | $4,240,000 | 82919 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $3,392,000 $848,000 | 2013 2013 | ODOT |
| Description: MINOR REHABILITATION, BRIDGEWORK AND INTERSECTON IMPROVEMENTS AT SR 43, FROM SUMMIT COUNTY LINE TO SR 183 | ||||
| EAST SUMMIT ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | KENT | CAPACITY | $12,574,900 | 84546 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL CMAQ-A LOCAL CM | ENG ENG RW RW CONST CONST | $440,500 $110,100 $436,000 $109,000 $5,564,000 $3,346,600 $2,227,700 | 2012 2012 2013 2013 2014 2014 2014 | KENT |
| Description: COORDINATED SIGNAL SYSTEM,NEW CENTER MEDIAN,IMPROVE LINCOLN ST INTERSECTION FROM SOUTH LINCOLN ST TO LOOP RD | ||||
| SR 82 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | MANTUA TWP,HIRAM TWP,WINDHAM TWP,HIRAM,GARRETTSVILLE | PRESERVATION | $3,035,000 | 84592 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $2,428,000 $607,000 | 2014 2014 | ODOT |
| Description: RESURFACING, MISCELLANEOUS BRIDGE WORK AND CULVERT WORK FROM SPENCER PARK RD TO TRUMBULL COUNTY LINE | ||||
| SR 14, SR 183 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | ATWATER TWP,EDINBURG TWP,DEERFIELD TWP,RAVENNA,KENT | PRESERVATION | $3,040,000 | 84593 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $2,432,000 $608,000 | 2014 2014 | ODOT |
| Description: RESURFACING WORK ON FOUR BRIDGES FROM TALLMADGE RD TO US 224/SR 225, SR 183 FROM US 224 TO SR 14 | ||||
| SR 5 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | RAVENNA TWP,CHARLESTOWN TWP,PARIS TWP | PRESERVATION | $2,740,000 | 84596 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| NHS STATE | CONST CONST | $2,192,000 $548,000 | 2014 2014 | ODOT |
| Description: RESURFACING WORK ON SIX BRIDGES FROM RIDDLE RD TO TRUMBULL CO LINE | ||||
| THE PORTAGE HIKE & BIKE,TANNERY PARK SECTION | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | KENT | ENHANCEMENT | $875,000 | 84984 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| TEP-A LOCAL | CONST CONST | $700,000 $175,000 | 2012 2012 | KENT |
| Description: CONSTRUCT MULTI-PURPOSE TRAIL FROM FRED FULLER PARK/WATER RECLAIMATION FACILITY TO JOHN BROWN TANNERY PARK | ||||
| SR 5 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | RAVENNA TWP | OPERATIONAL | $920,000 | 85296 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP STATE HSP STATE | RW RW CONST CONST | $45,000 $5,000 $858,500 $11,500 | 2012 2012 2013 2013 | ODOT |
| Description: RECONFIGURE INTERSECTION LANE RESTRICTIONS AT NEW MILFORD RD | ||||
| SR 43,SR 59,SR 261 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | BRIMFIELD TWP,FRANKLIN TWP,RAVENNA TWP,RAVENNA,KENT | PRESERVATION | $2,090,000 | 86930 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| NHS STP-S STATE LOCAL | CONST CONST CONST CONST | $1,320,000 $352,000 $401,500 $16,500 | 2015 2015 2015 2015 | ODOT |
| Description: RESURFACING WORK ON SIX BRIDGES SR 43 FROM KENT NORTH CORP LINE TO ALTA ST, SR 59 FROM MENOUGH RD TO SR 5, SR 261 FROM .77 MILES WEST OF SUMMIT RD TO SR 59 | ||||
| SR 303 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | SHALERSVILLE TWP,FREEDOM TWP | PRESERVATION | $1,402,500 | 86932 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $1,122,000 $280,500 | 2015 2015 | ODOT |
| Description: RESURFACING AND BRIDGE REPLACEMENT FROM SR 44 TO SR 700 | ||||
| SR 43,SR 82 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | AURORA | PRESERVATION | $1,760,000 | 86963 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| NHS STP-S STATE LOCAL | CONST CONST CONST CONST | $968,000 $440,000 $22,000 $330,000 | 2015 2015 2015 2016 | ODOT |
| Description: RESURFACING, BRIDGE DECK OVERLAY AT SR 43 FROM SOUTH CORP LIMIT TO GEAUGA COUNTY LINE, SR 82 FROM SUMMIT COUNTY LINE TO SR 43 | ||||
| SUMMIT RD,CR 148 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | FRANKLIN TWP | OPERATIONAL | $626,400 | 87664 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL | CONST CONST | $501,100 $125,300 | 2013 2013 | PORTAGE COUNTY ENGINEER |
| Description: CONSTRUCT ROUNDABOUT AT POWDER MILL RD | ||||
| WEST MAIN ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | KENT | PRESERVATION | $901,000 | 88357 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR-C LOCAL | CONST CONST | $720,800 $180,200 | 2012 2012 | PORTAGE COUNTY ENGINEER |
| Description: BRIDGE REHABILITATION OVER CUYAHOGA RIVER AND CSX RAILROAD | ||||
| ROCK SPRING RD,CR 52 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | CHARLESTOWN TWP | PRESERVATION | $1,971,000 | 88372 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR-C LOCAL | CONST CONST | $1,576,800 $394,200 | 2012 2012 | PORTAGE COUNTY ENGINEER |
| Description: BRIDGE REHABILITATION OVER WEST BRANCH RESERVOIR | ||||
| SR 59 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | FRANLIN TWP | ENHANCEMENT | $230,800 | 88501 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| TEP-A LOCAL TEP-A LOCAL | RW RW CONST CONST | $4,600 $1,200 $180,000 $45,000 | 2012 2012 2013 2013 | PORTAGE COUNTY ENGINEER |
| Description: SIDEWALK AND PEDESTRIAN SIGNALS FROM WEST FRANKLIN TWP LINE TO RHODES RD | ||||
| THE PORTAGE HIKE & BIKE, KSU GATEWAY SECTION | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | KENT | ENHANCEMENT | $2,383,700 | 88517 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| TEP-A LOCAL | CONST CONST | $700,000 $1,683,700 | 2012 2012 | KENT |
| Description: CONSTRUCT 24 FOOT WIDE MULTI-PURPOSE TRAIL FROM SR 59 TO LINCOLN ST | ||||
| RANDOLPH RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | MOGADORE | PRESERVATION | $265,000 | 88596 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $233,200 $58,300 | 2012 2012 | MOGADORE |
| Description: RESURFACING FROM CLEVELAND AVE TO EAST CORP LINE | ||||
| FRED FULLER PARK | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | KENT | PRESERVATION | $1,210,000 | 90582 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR LOCAL | CONST CONST | $968,000 $242,000 | 2013 2013 | KENT |
| Description: BRIDGE REPLACEMENT AT FRED FULLER PARK | ||||
| IR 76 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | BRIMFIELD TWP | PRESERVATION | $2,290,500 | 91094 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STATE BR STATE | ENG CONST CONST | $10,500 $2,052,000 $228,000 | 2012 2012 2012 | ODOT |
| Description: RECONSTRUCT DECTS AND PAINT BRIDGES AT SHERMAN RD AND SANDY LAKE RD | ||||
| IR 76 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | PALMYRA TWP | PRESERVATION | $390,000 | 92144 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STATE IM STATE | PE CONST CONST | $5,000 $346,500 $38,500 | 2012 2013 2013 | ODOT |
| Description: SLIDE REPAIR ON I-76 EB NEAR PARKMAN RD | ||||
| SR 5 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | ROOTSTOWN TWP,RAVENNA TWP | PRESERVATION | $1,320,000 | 92275 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S NHS STATE | CONST CONST CONST | $981,200 $74,800 $264,000 | 2012 2012 2012 | ODOT |
| Description: RESURFACING, MINOR BRIDGE WORK | ||||
| CRAIN AVE | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | KENT | PRESERVATION | $113,000 | 92656 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $82,400 $20,600 | 20 132 013 | KENT |
| Description: RESURFACING FROM EAST OF LAKE ST TO N WILLOW ST | ||||
| HIGHLAND AVE,DIAMOND ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | RAVENNA | PRESERVATION | $163,400 | 92707 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $118,700 $29,700 | 2013 2013 | RAVENNA |
| Description: RESURFACING ON HIGHLAND AVE FROM SYCAMORE TO DIAMOND ST AND ON DIAMOND ST FROM HIGHLAND AVE TO MILL ST | ||||
| TALLMADGE RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| PORTAGE | ROOTSTOWN TWP | PRESERVATION | $297,000 | 92710 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $237,600 $59,400 | 2013 2013 | PORTAGE COUNTY ENGINEER |
| Description: RESURFACING FROM NEW MILFORD RD TO INDUSTRY RD | ||||
| IR 271 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | RICHFIELD,RICHFIELD TWP | PRESERVATION | $55,184,000 | 18710 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| IM STATE | CONST CONST | $49,666,500 $5,517,500 | 2013 2013 | ODOT |
| Description: PAVEMENT REPLACEMENT AND BRIDGE WORK FROM 0.42 MILES SOUTH OF SR 176 TO THE OHIO TURNPIKE BRIDGE | ||||
| SUMMIT RD,CR 53 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | NORTON | PRESERVATION | $385,000 | 22077 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR-C LOCAL | CONST CONST | $308,000 $77,000 | 2015 2015 | SUMMIT COUNTY ENGINEER |
| Description: BRIDGE REHABILITATION OVER WOLF CREEK | ||||
| COPLEY RD,SR 162 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | COPLEY TWP,AKRON | PRESERVATION | $2,135,000 | 25552 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE LOCAL | CONST CONST CONST | $1,708,000 $283,000 $144,000 | 2013 2013 2013 | ODOT |
| Description: MINOR REHABILITATION AND RESURFACING FROM MEDINA COUNTY LINE TO IR 77 | ||||
| IR 76,IR 277,US 224 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON,COVENTRY TWP | PRESERVATION | $16,640,600 | 76351 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| IM NHS STATE | CONST CONST CONST | $12,122,100 $2,537,300 $1,981,200 | 2012 2012 2012 | ODOT |
| Description: MINOR REHABILITATION, RESURFACING, MISCELLANEOUS BRIDGE WORK FROM AKRON WEST CORP LINE TO 0.19 MILES EAST OF KELLY AVE | ||||
| BRECKSVILLE RD,SR 21 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | RICHFIELD | PRESERVATION | $671,000 | 76388 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $536,800 $134,200 | 2015 2015 | ODOT |
| Description: MINOR REHABILITATION AND RESURFACING FROM IR-77 TO CUYAHOGA COUNTY LINE | ||||
| IR 77 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | GREEN,COVENTRY TWP | PRESERVATION | $5,890,000 | 76391 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| IM STATE | CONST CONST | $5,301,000 $589,000 | 2014 2014 | ODOT |
| Description: MINOR REHABILITATION AND RESURFACING FROM SR 241 TO KILLIAN RD | ||||
| IR 77 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BATH TWP | PRESERVATION | $9,700,000 | 76403 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| IM STATE IM STATE | ENG ENG CONST CONST | $630,000 $70,000 $6,930,000 $770,000 | 2012 2012 2012 2012 | ODOT |
| Description: REDECK SEVEN BRIDGES FROM CLEVELAND MASSILLON RD TO RICHFIELD CORP LINE | ||||
| IR 271 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | NORTHFIELD CENTER TWP,MACEDONIA | PRESERVATION | $7,340,000 | 76406 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| IM STATE | CONST CONST | $6,606,000 $734,000 | 2012 2012 | ODOT |
| Description: MINOR REHABILITATION, RESURFACING AND WORK TO SIX BRIDGES FROM 0.19 MILES NORTH OF OLDE EIGHT RD TO CUYAHOGA COUNTY LINE | ||||
| MANCHESTER RD,SR 93,TURKEYFOOT LAKE RD,SR 619 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | NEW FRANKLIN | OPERATIONAL | $1,600,000 | 76436 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL STP-A LOCAL | RW RW CONST CONST | $80,000 $20,000 $1,320,000 $330,000 | 2014 2014 2015 2015 | NEW FRANKLIN |
| Description: TURN LANES AND SIGNAL UPGRADE AT INTERSECTION | ||||
| MANCHESTER RD,SR 93 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | CONVENTRY TWP | CAPACITY | $5,719,500 | 76437 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A STP-S HSP STATE LOC | CONST CONST CONST CONST C | $784,300 $60,000 $4,500 $3,845,700 $1,025,000 | 2013 2013 2013 2013 2013 | ODOT |
| Description: WIDEN TO FIVE LANES AND INTERSECTION IMPROVEMENTS FROM SOUTH OF ROBINSON AVE TO NORTH OF CORMANY RD | ||||
| SR 59 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $11,782,000 | 76849 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $9,425,600 $2,356,400 | 2014 2014 | ODOT |
| Description: MINOR REHABILITATION AND MISC WORK TO EIGHTEEN BRIDGES FROM IR 76/77 TO E MARKET ST | ||||
| IR 76 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | CAPACITY | $4,700,000 | 77269 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| IM STATE DISC LOCAL | ENG ENG ENG ENG | $900,000 $100,000 $500,000 $55,600 | 2012 2012 2012 2012 | ODOT |
| Description: RECONFIGURE MAIN/BROADWAY AND GRAN/WOLF LEDGES INTERCHANGES | ||||
| IR 76 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $6,680,000 | 77876 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR IM STATE | CONST CONST CONST | $2,700,000 $3,312,000 $668,000 | 2015 2015 2015 | ODOT |
| Description: PAVEMENT REHABILITATION AND MULTIPLE BRIDGE DECK OVERLAYS FROM INMAN ST TO GILCHRIST RD | ||||
| SR 8 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $4,157,500 | 77880 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| NHS STATE LOCAL | CONST CONST CONST | $3,252,000 $813,000 $92,500 | 2012 2012 2012 | ODOT |
| Description: RESURFACING, MISCELLANEOUS BRIDGE WORK AND SIGN UPGRADE FROM HIGH LEVEL BRIDGE TO AKRON NORTH CORP LINE | ||||
| IR 77 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON, FAIRLAWN,COPLEY TWP | ENHANCEMENT | $700,000 | 80630 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STATE LOCAL | CONST CONST | $480,000 $220,000 | 2012 2012 | AKRON |
| Description: LANDSCAPING FROM COPLEY RD TO SR 21 | ||||
| LAUBY RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | GREEN | OPERATIONAL | $1,836,100 | 80665 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| DISC HSP LOCAL DISC HSP L | ENG ENG ENG CONST CONST C | $33,400 $29,100 $205,700 $962,000 $333,000 $37,000 | 2012 2012 2012 2013 2013 2013 | GREEN |
| Description: STANDAR LANE WIDTH FROM AKRON CANTON AIRPORT DR TO GREENSBURG RD, IMPROVE LAUBY RD/GREENSBURGH RD INTERSECTION | ||||
| EVANS AVE | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | OPERATIONAL | $8,000,000 | 80684 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| DISC DISC STP-S LOCAL | PE RW CONST CONST | $367,500 $456,000 $6,216,800 $327,200 | 2012 2013 2014 2014 | AKRON |
| Description: RAILROAD GRADE SEPARATION OF EVANS AVE OVER CSX RAILROAD | ||||
| TURKEYFOOTLAKE RD,SR 619 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | GREEN | PRESERVATION | $2,025,000 | 81599 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR STATE LOCAL | CONST CONST CONST | $1,612,000 $55,000 $358,000 | 2013 2013 2013 | ODOT |
| Description: RESURFACING AND BRIDGE REPLACEMENT FROM NEW FRANKLIN EAST CORP LINE TO STARK COUNTY LINE | ||||
| STATE RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | CUYAHOGA FALLS | OPERATIONAL | $9,185,000 | 81605 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $5,260,000 $3,925,000 | 2013 2013 | CUYAHOGA FALLS |
| Description: TURN LANE, UPGRADE SIGNALS, BIKE LANE AND IMPROVE DRAINAGE FROM BATH RD TO STEELS CORNERS RD | ||||
| IR 77 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | RICHFIELD | PRESERVATION | $6,260,000 | 81632 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| IM STATE | CONST CONST | $5,634,000 $626,000 | 2015 2015 | ODOT |
| Description: RESURFACING AND MISCELLANEOUS BRIDGE WORK FROM RICHFIELD SOUTH CORP LINE TO CUYAHOGA COUNTY LINE | ||||
| SR 18 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | COPLEY TWP,BATH TWP,FAIRLAWN | PRESERVATION | $4,418,500 | 81633 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| NHS STATE LOCAL | CONST CONST CONST | $3,534,800 $603,700 $280,000 | 2015 2015 | ODOT |
| Description: RESURFACING AND MISCELLANEOUS RIDGE WORK FROM MEDINA COUNTY LINE TO AKRON WEST CORP LINE | ||||
| SR 82 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | MACEDONIA,TWINSBURG | CAPACITY | $7,155,000 | 81656 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL STP-A STP-A HSP | ENG ENG RW CONST CONST CO | $585,000 $65,000 $308,000 $3,867,000 $797,000 $320,000 $80,000 $1,132,400 | 2012 2012 2014 2015 2015 2015 2015 2015 | MACEDONIA |
| Description: RECONSTRUCTION, TURN LANES AND BIKE LANES FROM EAST OF CROW DR TO CHAMBERLIN RD | ||||
| CANTON RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | SPRINGFIELD TWP, LAKEMORE | OPERATIONAL | $4,880,300 | 82594 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL HSP LOCAL | ENG ENG CONST CONST | $287,500 $31,900 $1,851,500 $2,493,500 | 2012 2012 2014 2014 | SUMMIT COUNTY ENGINEER |
| Description: STANDARD LANE WIDTH, ADD CONCRETE MEDIAN AND CORRECT VERTICAL CURVE FROM SANITARIUM RD TO WATERLOO RD | ||||
| RAVENNA RD,OLD MILL RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TWINSBURG TWP | PRESERVATION | $3,269,000 | 82787 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL BR-C HSP LOCAL | RW RW CONST CONST CONST | $215,200 $53,800 $1,360,000 $1,040,000 $600,000 | 2012 2012 2015 2015 2015 | SUMMIT COUNTY ENGINEER |
| Description: RECONSTRUCT RAVENNA RD BRIDGE OVER TINKERS CREEK, RECONSTRUCT RAVENNA RD/OLD MILL/STOW RD INTERSECTIONS | ||||
| SR 91 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | SPRINGFIELD TWP, TALLMADGE | PRESERVATION | $285,000 | 82910 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S LOCAL | CONST CONST | $228,000 $57,000 | 2013 2013 | ODOT |
| Description: RESURFACING FROM US 224 TO MCELWAIN DR, TALLMADGE CIRCLE, 0.04 MILES NORTH OF OVERDALE DR TO 0.06 MI SOUTH OF HOWE RD | ||||
| STREETSBORO RD,SR 303 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | HUDSON | PRESERVATION | $1,435,000 | 82914 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE LOCAL | CONST CONST CONST | $1,148,000 $40,000 $734,000 | 2013 2013 2013 | ODOT |
| Description: RESURFACING AND MINOR WORK TO THREE BRIDGES FROM WEST CORP LINE TO EAST CORP LINE | ||||
| HIGH ST,SR 261,WILBETH RD,SR 764 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $720,000 | 82915 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S LOCAL | CONST CONST | $576,000 $144,000 | 2013 2013 | ODOT |
| Description: RESURFACING AND BRIDGE DECK OVERLAY - HIGH ST FROM CHURCH ST TO EXCHANGE ST AND WILBETH RD FROM SR 93 TO S. MAIN ST | ||||
| DARROW RD,SR 91,STREETSBORO RD,SR 303 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | STOW,HUDSON | OPERATIONAL | $4,050,000 | 82956 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL STP-S STP-A S | RW RW CONST CONST CONST C | $80,000 $20,000 $2,876,000 $560,000 $719,000 $190,000 | 2014 2014 2015 2015 2015 2015 | STOW |
| Description: TURN LANES, NEW SIGNAL, REPLACE THREE SPAN BRIDGE WITH A PRECAST STRUCTURE AT SR 91 FROM FISHCREEK FRD TO NORTON RD AND SR 303 BRIDGE OVER MUD BROOK | ||||
| DART AVE | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $805,000 | 83577 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR LOCAL | CONST CONST | $644,000 $161,000 | 2012 2012 | ODOT |
| Description: BRIDGE REPLACEMENT AT DART AVE RAMP | ||||
| 31ST ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BARBERTON | PRESERVATION | $660,000 | 84395 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR-C LOCAL | CONST CONST | $415,200 $244,800 | 2012 2012 | SUMMIT COUNTY ENGINEER |
| Description: RECONSTRUCT BRIDGE WITH INCREASED LANE AND SHOULDER WIDTHS OVER HUDSON RUN | ||||
| ENGLEWOOD ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | OPERATIONAL | $9,474,000 | 84396 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A CMAQ-A STP-A LOCAL | RW CONST CONST CONST | $3,000,000 $500,000 $1,872,000 $4,102,000 | 2012 2013 2013 2013 | AKRON |
| Description: RECONSTRUCTION AND EXTEND FROM MARTHA AVE TO MASSILLON RD | ||||
| SEIBERLING WAY (PHASE 1) | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | CAPACITY | $6,059,300 | 84397 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A CMAQ-A STP-A LOCAL | RW CONST CONST CONST | $500,000 $1,270,000 $768,300 $3,521,000 | 2012 2014 2014 2014 | AKRON |
| Description: CONSTRUCT NEW ROAD, NEW BRIDGE OVER LITTLE CUYAHOGA RIVER FROM ENGLEWOOD ST TO EAGLE ST | ||||
| SR 82 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | SAGAMORE HILLS TWP,NORTHFIELD CENTER TWP,MACEDONIA | PRESERVATION | $1,423,500 | 84563 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE LOCAL | CONST CONST CONST | $1,138,800 $185,700 $99,000 | 2014 2014 2014 | ODOT |
| Description: RESURFACING FROM CUYAHOGA COUNTY LINE TO FREEWAY DR AND SHEPARD DR TO MACEDONIA EAST CORP LIMIT | ||||
| CANTON RD,SR 91,MANCHESTER RD,SR 93 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $645,000 | 84570 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S LOCAL | CONST CONST | $516,000 $129,000 | 2014 2014 | ODOT |
| Description: RESURFACING AT SR 91 FROM WEDGEWOOD DR TO SR 18 AND AT SR 92 FROM 0.06 MILES SOUTH OF LAKEVIEW AVE TO EAST AVE | ||||
| IR 76 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | NORTON | PRESERVATION | $3,969,500 | 84629 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STATE BR IM STATE | RW CONST CONST CONST | $5,000 $1,782,000 $1,786,000 $396,000 | 2013 2014 2014 2014 | ODOT |
| Description: REPLACE TWO BRIDGES, CLARK MILL RD BRIDGE AND SUMMIT RD BRIDGE OVER IR 76 | ||||
| SEIBERLING WAY (PHASE 2) | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | CAPACITY | $10,000,000 | 84907 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $7,000,000 $3,000,000 | 2012 2012 | AKRON |
| Description: CONSTRUCT NEW STREET FROM EAGLE ST TO MASSILLON RD, CONSTRUCT ROUNDABOUT AT EAGLE ST | ||||
| GRAHAM RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | CUYAHOGA FALLS,STOW | OPERATIONAL | $4,988,900 | 84977 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP CMAQ-A LOCAL CMAQ-A H | RW RW RW CONST CONST CONS | $500,000 $80,000 $75,600 $2,400,000 $1,200,000 $733,300 | 2012 2012 2012 2013 2013 2013 | STOW |
| Description: TURN LANES, SIGNAL COORDINATION AND RESURFACING FROM BATH RD TO SR 8 | ||||
| TALLMADGE TRAIL | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TALLMADGE | ENHANCEMENT | $1,825,000 | 84995 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| TEP-A LOCAL | CONST CONST | $700,000 $1,125,000 | 2012 2012 | SUMMIT COUNTY METRO-PARKS |
| Description: UPGRADE EXISITING TRAIL FROM SOUTHWEST AVE TO HOWE RD, CONSTRUCT NEW MULTI-PUROPSE TRAIL FROM HOWE RD TO KENT | ||||
| CLEVELAND MASSILLON RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | NORTON | OPERATIONAL | $4,807,000 | 85076 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $3,845,600 $961,400 | 2014 2014 | NORTON |
| Description: RECONSTRUCTION FROM GREENWICH RD TO 1-76/US 224 | ||||
| SR 91,DARROW RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TWINSBURG | OPERATIONAL | $5,987,300 | 85078 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL STP-A LOCAL STP | ENG ENG RW RW CONST CONST | $371,000 $41,200 $480,000 $120,000 $3,908,100 $977,000 | 2012 2012 2013 3013 2014 2014 | TWINSBURG |
| Description: RECONSTRUCTION AND TURN LANES FROM POST RD TO GLENWOOD AVE | ||||
| RAVENNA RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | HUDSON | PRESERVATION | $1,275,000 | 85159 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR-C LOCAL | CONST CONST | $1,020,000 $255,000 | 2013 2013 | SUMMIT COUNTY ENGINEER |
| Description: BRIDGE REPLACEMENT OVER TINKERS CREEK | ||||
| NORTH ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $1,530,800 | 85161 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR-C LOCAL | CONST CONST | $1,128,000 $418,000 | 2013 2013 | SUMMIT COUNTY ENGINEER |
| Description: BRIDGE REPLACEMENT OVER LITTLE CUYAHOGA RIVER | ||||
| STATE ST BRIDGE | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $7,225,000 | 86053 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR LOCAL | CONST CONST | $2,500,000 $4,725,000 | 2013 2013 | AKRON |
| Description: BRIDGE REPLACEMENT OVER OHIO CANAL | ||||
| AKRON CLEVELAND RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BOSTON HEIGHTS | PRESERVATION | $4,875,800 | 86154 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR LOCAL | CONST CONST | $2,750,000 $2,125,800 | 2014 2014 | BOSTON HEIGHTS |
| Description: BRIDGE REPLACEMENT OVER METROPAKRS TRAIL | ||||
| 31ST ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BARBERTON | OPERATIONAL | $1,727,900 | 86923 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL HSP LOCAL | ENG ENG CONST CONST | $46,300 $5,100 $1,200,000 $133,300 | 2012 2012 2014 2014 | BARBERTON |
| Description: ADD MEDIAN TURN LANE AND SIGNAL UPGRADE AT SHANNON AVE FROM WOOSTER RD TO SHANNON AVE | ||||
| CLEVELAND AVE,SR 532 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | MOGADORE | OPERATIONAL | $110,000 | 86928 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP | CONST | $110,000 | 2013 | ODOT |
| Description: UPGRADE SIGNAL WITH 12 INCH HEADS AND BACKPLATE AT MOGADORE RD | ||||
| SR 8 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | NORTHFIELD | PRESERVATION | $550,000 | 86937 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $440,000 $110,000 | 2015 2015 | ODOT |
| Description: RESURFACING FROM NORTHFIELD CORP LINE TO CUYAHOGA COUNTY LINE | ||||
| MANCHESTER RD,SR 93 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | NEW FRANKLIN,COVENTRY TWP | PRESERVATION | $2,272,500 | 86938 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE LOCAL | CONST CONST CONST | $1,818,000 $129,500 $325,000 | 2015 2015 2015 | ODOT |
| Description: RESURFACING AND MISCELLANEOUS WORK TO FOUR BRIDGES FROM STARK COUNTY LINE TO 0.18 MILES SOUTH OF STATE ST, BRIDGE OVER TUSC RIVER TO AKRON SOUTH CORP LINE (CARNEGIE AVE) SR 619 FROM BARBERTON S. CORP TO SR 93 | ||||
| SR 91,DARROW RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TWINSBURG,TWINSBURG TWP | PRESERVATION | $1,540,000 | 86954 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S BR STATE LOCAL | CONST CONST CONST CONST | $1,122,000 $110,000 $66,000 $242,000 | 2015 2015 2015 2015 | ODOT |
| Description: RESURFACING, MISCELLANEOUS WORK TO TWO BRIDGES FROM HUDSON NORTH CORP LINE TO 0.05 MILES SOUTH OF POST RD | ||||
| IR 76 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $2,500,000 | 86977 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| IM STATE | CONST CONST | $2,250,000 $250,000 | 2012 2012 | ODOT |
| Description: CONCRETE OVERLAY ON THREE BRIDGES AT KENMORE LEG OF SUM 1R-76 | ||||
| IR 76/77 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $19,250,000 | 86979 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STATE STATE IM STATE | ENG RW CONST CONST | $750,000 $2,750,000 $14,850,000 $1,650,000 | 2012 2013 2015 2015 | ODOT |
| Description: BRIDGE REPLACEMENT, REMOVE THREE BRIDGES, RELOCATE JOHNSTON ST BETWEEN SPICER ST AND BROWN ST | ||||
| EAST MARKET ST,SR 18 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $1,816,100 | 86996 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| NHS BR STATE LOCAL | CONST CONST CONST CONST | $744,000 $582,100 $186,000 $218,300 | 2015 2015 2015 2015 | ODOT |
| Description: DECK REPLACEMENT, REPLACE ONE STRUCTURE AT BRITTAIN RD OVER SR-18 | ||||
| DARROW RD,SR 91 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | STOW | PRESERVATION | $275,000 | 87756 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STATE | CONST | $275,000 | 2013 | ODOT |
| Description: BRIDGE REPLACEMENT SOUTH OF SR 59 | ||||
| SR 18 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | OPERATIONAL | $1,200,000 | 87783 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| CMAQ-A STP-S LOCAL | CONST CONST CONST | $568,000 $490,000 $142,000 | 2013 2013 | AKRON |
| Description: UPGRADE SIGNAL SYSTEM, INTERCONNECT, PRE-EMPTION FROM GOODKIRK ST TO FIRESTATION 2 AND GOODKIRK ST/FOUNTAIN ST FROM EXCHANGE ST TO PERKINS AVE | ||||
| BANK ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $1,251,800 | 88009 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR-C LOCAL | CONST CONST | $1,001,400 $250,400 | 2013 2013 | SUMMIT COUNTY ENGINEER |
| Description: REPLACE BRIDGE SUPERSTRUCTURE, MODIFY EXISTING ABUTMENTS AND RECONSTRUCT APPROACHES OVER LITTLE CUYAHOGA RIVER | ||||
| ARLINGTON RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | COVENTRTY TWP,SPRINGFIELD TWP | OPERATIONAL | $1,410,000 | 88528 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| CMAQ-A LOCAL CMAQ-A LOCAL | RW RW CONST CONST | $160,000 $40,000 $880,000 $330,000 | 2014 2014 2015 2015 | SUMMIT COUNTY ENGINEER |
| Description: SIDEWALK AND RAMPS, NB TURN LANE AT WARNER RD, INTERCONNECT TRAFFIC SIGNALS AND RESURFACE FROM KILLIAN RD TO KRUMROY RD, FROM GREEN NORTH CORP LINE TO AKRON SOUTH CORP LINE | ||||
| TOWPATH TRAIL (PARK EAST) | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | ENHANCEMENT | $875,000 | 88529 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| TEP-A LOCAL | CONST CONST | $700,000 $175,000 | 2013 2013 | AKRON |
| Description: CONSTRUCT MULTI-PURPOSE TRAIL WITH BRIDGE, LIGHTING AND SIGNS FROM THORNTON ST TO BARTGES ST | ||||
| IR 76,MARTHA AVE | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | OPERATIONAL | $750,000 | 88533 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| DISC | PE | $750,000 | 2012 | AKRON |
| Description: CORRIDOR STUDY | ||||
| CHAMBERLIN RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TWINSBURG | PRESERVATION | $570,000 | 88535 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $456,000 $114,000 | 2012 2012 | TWINSBURG |
| Description: RESURFACING FROM SR 82 TO RAVENNA RD | ||||
| NORTON RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | HUDSON,STOW | PRESERVATION | $1,309,000 | 88544 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $250,800 $788,700 | 2013 2013 | HUDSON AND STOW |
| Description: RESURFACING FROM SR 91 TO STOW RD | ||||
| STOW RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | HUDSON | PRESERVATION | $1,000,000 | 88545 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $800,000 $200,000 | 2012 2012 | HUDSON |
| Description: RESURFACING FROM NORTON RD TO SR 303 | ||||
| MAIN ST,SR 91,PROSPECT ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | HUDSON | OPERATIONAL | $700,000 | 88548 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL STP-A LOCAL | RW RW CONST CONST | $80,000 $20,000 $480,000 $120,000 | 2013 2013 2014 2014 | HUDSON |
| Description: TURN LANES, UPDATE SIGNAL, CURB AND GUTTER AT PROSPECT ST | ||||
| FREEDOM SECONDARY RAIL TRAIL (NORTHSIDE) | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON,TALLMADGE | ENHANCEMENT | $5,137,500 | 88550 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| TEP-A LOCAL | CONST CONST | $700,000 $4,437,500 | 2014 2014 | SUMMIT COUNTY METRO-PARKS |
| Description: CONSTRUCT MULTI-PURPOSE TRAIL WITH BRIDGE AND LOOP RAMP FROM NORTHSIDE TRAIN STATION TO SOUTHWEST AVE | ||||
| NORTHSIDE TRAIN STATION CONNECTOR | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | ENHANCEMENT | $875,000 | 88552 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| TEP-A LOCAL | CONST CONST | $700,000 $175,000 | 2013 2013 | AKRON |
| Description: CONSTRUCT MULTI-PURPOSE TRAIL WITH BRIDGE FROM BEECH ST TRAIL HEAD TO NORTHSIDE TRAIN STATION | ||||
| TALLMADGE AVE,SR 261 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | OPERATIONAL | $1,250,000 | 88556 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL STP-A LOCAL | RW RW CONST CONST | $320,000 $80,000 $680,000 $170,000 | 2013 2013 2014 2014 | AKRON |
| Description: REALIGN INTERSECTION AT DAYTON ST | ||||
| COPLEY RD,SR 162 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | OPERATIONAL | $2,625,000 | 88968 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| CMAQ-A LOCAL | CONST CONST | $2,100,000 $525,000 | 2015 2015 | AKRON |
| Description: UPGRADE SIGNAL SYSTEM AND INTERCONNECT VIDEO FROM COLLIER RD TO GLENDALE AVE | ||||
| WEST EXCHANGE ST,CEDAR ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | OPERATIONAL | $3,000,000 | 88990 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| CMAQ-A LOCAL | CONST CONST | $2,400,000 $600,000 | 2015 2015 | AKRON |
| Description: UPGRADE SIGNAL SYSTEM AND INTERCONNECT VIDEO FROM DELIA AVE TO BOWERY ST | ||||
| SR 91 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | SPRINGFIELD TWP | OPERATIONAL | $350,000 | 89113 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP STATE | ENG ENG | $315,000 $35,000 | 2012 2012 | ODOT |
| Description: TURN LANES, ACCESS MANAGEMENT AND PROFILE ADJUSTMENTS AT INTERSECTION OF SR 91 AND US 224 AND FROM ARCADIA TO LINWOOD | ||||
| CANTON RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | SPRINGFIELD TWP, LAKEMORE | OPERATIONAL | $107,100 | 89306 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL HSP LOCAL | ENG ENG CONST CONST | $16,200 $1,800 $81,000 $8,100 | 2012 2012 2012 2012 | SUMMIT COUNTY ENGINEER |
| Description: NEW TRAFFIC SIGNAL AT SPRINGFIELD LAKE DRIVE | ||||
| THORNTON ST BRIDGE | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $700,500 | 89456 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR LOCAL | CONST CONST | $560,400 $140,100 | 2013 2013 | AKRON |
| Description: ASPHALT OVERLAY, REPAIRS TO EXPANSION JOINTS, WINGWALLS, SIDEWALKS AND CURBS FROM BROADWAY TO WOLF LEDGES | ||||
| WOOSTER RD,SR 619 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BARBERTON | OPERATIONAL | $445,000 | 90310 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL HSP LOCAL | ENG ENG ENG ENG | $202,000 $22,500 $198,500 $22,000 | 2012 2012 2014 2014 | BARBERTON |
| Description: IMPROVE INTERSECTION WITH RAMPS AT IR 76/US 224 | ||||
| MASSILLON RD,SR 241 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | GREEN | CAPACITY | $400,000 | 90415 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP LOCAL | ENG ENG | $360,000 $40,000 | 2012 2012 | GREEN |
| Description: WIDENING RABER RD TO SR 619 | ||||
| SWINEHART AVE BRIDGE | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $600,000 | 90642 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR LOCAL | CONST CONST | $480,000 $120,000 | 2014 2014 | AKRON |
| Description: BRIDGE REPLACEMENT OVER MUD RUN DITCH | ||||
| WHITE POND DR (PHASE 3) | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON,COPLEY TWP | PRESERVATION | $3,157,500 | 90890 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| DISC LOCAL DISC DISC LOCA | ENG ENG RW CONST CONST | $606,000 $151,500 $728,000 $922,000 | 2012 2012 2013 2013 | AKRON |
| Description: RESURFACING AND INTERSECTION IMPROVEMENTS FROM I-77 TO SR 162 COPLEY RD | ||||
| SR 91,DARROW RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TWINSBURG | PRESERVATION | $300,000 | 90944 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A STATE LOCAL | CONST CONST CONST | $150,000 $75,000 $75,000 | 2012 2012 2012 | TWINSBURG |
| Description: RESURFACING UNDER 1-480 BRIDGES | ||||
| STEESE RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | GREEN | OPERATIONAL | $841,700 | 91003 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| SRTS LOCAL | CONST CONST | $55,700 $786,000 | 2014 2014 | GREEN |
| Description: STANDARD LANES, RESURFACING, TURN LANES AND SIDEWALKS FROM MASSILON RD TO SHRIVER RD | ||||
| CALL RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | STOW | ENHANCEMENT | $343,200 | 91004 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| SRTS SRTS | ENG CONST | $46,000 $297,200 | 2012 2012 | STOW |
| Description: NEW SIDEWALKS AND SPEED MONITORS AT CROSSWALKS CALL RD/VARIOUS SAFE ROUTES TO SCHOOL | ||||
| SR 82 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | SAGAMORE HILLS TWP | PRESERVATION | $2,750,000 | 91051 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR STATE | CONST CONST | $2,200,000 $550,000 | 2015 2015 | ODOT |
| Description: CONCRETE OVERLAY AND SEALING OF BRIDGE STRUCTURE OVER CUYAHOGA RIVER | ||||
| CLEVELAND MASSILLON RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BATH TOWNSHIP | ENHANCEMENT | $341,000 | 92216 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| DISC LOCAL | RW RW | $251,600 $89,400 | 2013 2013 | BATH TOWNSHIP |
| Description: ACQUISITION OF 7.5 ACRES FOR DEVELOPMENT OF A VISITOR INFORMATION WAYSIDE | ||||
| RAVENNA RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TWINSBURG TWP | PRESERVATION | $1,775,000 | 92240 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| BR-C LOCAL BR-C LOCAL | RW RW CONST CONST | $80,000 $20,000 $1,340,000 $335,000 | 2013 2013 2014 2014 | SUMMIT COUNTY ENGINEER |
| Description: BRIDGE REPLACEMENT OVER TINKERS CREEK | ||||
| NORTH HOWARD ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | ENHANCEMENT | $300,000 | 92252 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| DISC LOCAL | RW RW | $240,000 $60,000 | 2013 2013 | AKRON |
| Description: PROPERTY ACQUISITION AND REMOVAL OF THREE BILLBOARDS AT THE INTERSECTION OF N HOWARD ST AND NORTH ST | ||||
| AKRON PENINSULA RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BOSTON TWP | PRESERVATION | $705,000 | 92457 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| DISC | CONST | $705,000 | 2014 | SUMMIT COUNTY ENGINEER |
| Description: RESURFACING, SHOULDER RESTORATION, GUARDRAIL, AND PAVEMENT MARKINGS FROM CUYAHOGA FALLS NCL TO QUICK RD | ||||
| BRITTAIN RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | AKRON | PRESERVATION | $172,000 | 92592 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $128,000 $32,000 | 2013 2013 | AKRON |
| Description: RESURFACING FROM EVANS AVE TO TALLMADGE AVE | ||||
| BARLOW RD,TEREX RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | HUDSON | PRESERVATION | $700,000 | 92665 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $540,000 $135,000 | 2013 2013 | HUDSON |
| Description: RESURFACING ON BARLOW-TEREX RD FROM SR 91 TO THE RAILROAD TRACKS | ||||
| COMMERCE DR | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | STOW | PRESERVATION | $490,100 | 92666 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $373,700 $93,400 | 2013 2013 | STOW |
| Description: RESURFACING FROM HUDSON DR TO DARROW RD | ||||
| GHENT RD, CLEVELAND MASSILLON RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BATH TOWNSHIP | RESURFACING | $1,040,000 | 92667 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $800,000 $240,000 | 2013 2013 | SUMMIT COUNTY ENGINEER |
| Description: RESURFACING ON GHENT RD FROM SOUREK RD TO CLEVELAND MASSILLON RD AND CLEVELAND MASSILLON RD FROM SR 18 TO SPRINGSIDE DR | ||||
| GREENSBURG RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | GREEN | PRESERVATION | $390,400 | 92669 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $312,300 $78,100 | 2013 2013 | GREEN |
| Description: RESURFACING FROM ARLINGTON RD TO SHRIVER RD | ||||
| HINES HILL RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | HUDSON | PRESERVATION | $560,000 | 92671 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $432,000 $108,000 | 2013 2013 | HUDSON |
| Description: RESURFACING FROM THE HUDSON WEST CORP LINE TO PROSPECT ST | ||||
| HUDSON DR | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | HUDSON | PRESERVATION | $520,000 | 92674 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $400,000 $100,000 | 2013 2013 | HUDSON |
| Description: RESURFACING FROM NORTON RD TO TEREX RD | ||||
| HUDSON DR | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | STOW | PRESERVATION | $309,300 | 92675 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $230,600 $57,700 | 2013 2013 | STOW |
| Description: RESURFACING FROM MCCULLEY/HIBBARD RD TO SEASONS/NORTON RD | ||||
| MAYFAIR RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | GREEN | PRESERVATION | $200,800 | 92676 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $160,600 $40,200 | 2013 2013 | GREEN |
| Description: RESURFACING FROM THE GREEN SOUTH CORP LINE TO THE RAILROAD TRACKS | ||||
| RAVENNA ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | HUDSON | PRESERVATION | $470,000 | 92677 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $360,000 $90,000 | 2013 2013 | HUDSON |
| Description: RESURFACING FROM STOW RD TO THE HUDSON EAST CORP LINE | ||||
| RIVERVIEW RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BOSTON TWP | PRESERVATION | $830,000 | 92690 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $640,000 $160,000 | 2013 2013 | SUMMIT COUNTY ENGINEER |
| Description: RESURFACING FROM THE CUYAHOGA FALLS NORTH CORP LINE TO THE PENINSULA SOUTH CORP LINE | ||||
| SHEPARD RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TWINSBURG,MACEDONIA | PRESERVATION | $428,000 | 92704 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $334,400 $83,600 | 2013 2013 | TWINSBURG MACEDONIA |
| Description: RESURFACING FROM THE IR 480 BRIDGE TO RAVENNA RD | ||||
| STOW RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | STOW | PRESERVATION | $648,300 | 92705 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $506,600 $126,700 | 2013 2013 | STOW |
| Description: RESURFACING FROM CALL RD TO NORTON RD | ||||
| TALLMADGED RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | CUYAHOGA FALLS | PRESERVATION | $450,000 | 92706 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $340,000 $85,000 | 2013 2013 | CUYAHOGA FALLS |
| Description: RESURFACING FROM NEWBERRY ST TO CLYDE AVE | ||||
| MOGADORE RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | MOGADORE | PRESERVATION | $400,800 | 92712 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $312,600 $78,200 | 2013 2013 | MOGADORE |
| Description: RESURFACING FROM THE MOGADORE WEST CORP LINE TO GILCHRIST RD | ||||
| NEWTON ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TALLMADGE | PRESERVATION | $225,100 | 92713 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $180,100 $45,000 | 2013 2013 | TALLMADGE |
| Description: RESURFACING FROM THE TALLMADGE WEST CORP LINE TO SOUTHEAST AVE | ||||
| NORTHWEST AVE | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TALLMADGE | PRESERVATION | $322,000 | 92716 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $257,000 $64,300 | 2013 2013 | TALLMADGE |
| Description: NORTHWEST AVE FROM TALLMADGE CIRCLE TO THE TALLMADGE WEST CORP LINE | ||||
| STATE ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BARBERTON | PRESERVATION | $740,000 | 92719 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $576,000 $144,000 | 2013 2013 | BARBERTON |
| Description: RESURFACING FROM ROBINSON AVE TO HIGHLAND AVE | ||||
| STATE ST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BARBERTON | PRESERVATION | $333,800 | 92721 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $255,100 $63,800 | 2013 2013 | BARBERTON |
| Description: RESURFACING FROM WOOSTER RD TO ELMWOOD AVE | ||||
| SOUTH THOMAS RD | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | TALLMADGE | PRESERVATION | $267,000 | 92726 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| TEP-A LOCAL | CONST CONST | $213,600 $53,400 | 2013 2013 | TALLMADGE |
| Description: RESURFACING FROM TALLMADGE WEST CORP LINE TO WEST AVE | ||||
| WOOSTER RD NORTH | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BARBERTON | PRESERVATION | $312,900 | 92727 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $238,300 $59,600 | 2013 2013 | BARBERTON |
| Description: RESURFACING FROMPARK AVE TO HOPOCAN AVE | ||||
| WOOSTER RD WEST | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BARBERTON | PRESERVATION | $351,900 | 92729 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A LOCAL | CONST CONST | $269,500 $67,400 | 2013 2013 | BARBERTON |
| Description: RESURFACING FROM TAYLOR RD TO KRANCZ DR | ||||
| IR 80 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| SUMMIT | BOSTON HEIGHTS,HUDSON | CAPACITY | $34,000,000 | N/A |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| OTC | CONST | $34,000,000 | 2012 | OHIO TURNPIKE COMMISSION |
| Description: WIDEN TO SIX LANES AND RECONSTRUCT TOLL PLAZA FROM WEST OF SR 8 (MP 178.01) TO WEST OF PORTAGE COUNTY LINE (MP 185.32) | ||||
| County | Location | Class | Cost | PID |
|---|---|---|---|---|
| SUMMIT,PORTAGE | SUMMIT CO,PORTAGE CO | PRESERVATION | $2,000,000 | 82326 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-A STP-A STP-A STP-A | CONST CONST CONST CONST | $500,000 $500,000 $500,000 $500,000 | 2012 2013 2014 2015 | VARIOUS |
| Description: AMATS PAVEMENT REPAIR AND SIDEWALK RAMPS,PAVEMENT REPAIR AND SIDWALK RAMPS ON ODOT RESURFACING PROJECTS | ||||
| County | Location | Class | Cost | PID |
|---|---|---|---|---|
| SUMMIT,PORTAGE | SUMMIT CO,PORTAGE CO | OPERATIONAL | $400,000 | 83368,83369,90473,90474 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| CMAQ-A | ENG ENG ENG ENG | $100,000 $100,000 $100,000 $100,000 | 2012 2013 2014 2015 | AMATS |
| Description: AMATS AIR QUALITY ADVOCACY PROGRAM,PROMOTION OF ACTIVITIES TO IMPROVE AIR QUALITY SUCH AS RIDESHARE | ||||
| SR 57 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| WAYNE | CHIPPEWA TWP | PRESERVATION | $2,177,500 | 86725 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $1,742,000 $435,500 | 2012 2012 | ODOT |
| Description: RESURFACING FROM US 30 TO ORRVILLE SOUTH CORP LINE AND FROM ORRVILLE NORTH CORP LINE TO RITTMAN SOUTH CORP LINE | ||||
| SR 94 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| WAYNE | CHIPPEWA TWP | PRESERVATION | $4,235,500 | 86728 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $3,388,400 $847,100 | 2015 2015 | ODOT |
| Description: RESURFACING FROM ABANDON RR SOUTH OF MARSHALLVILLE TO MEDINA COUNTY LINE, SR 585 FROM SR 94 TO SUMMIT CO LINE | ||||
| SR 57 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| WAYNE | CHIPPEWA TWP | PRESERVATION | $1,584,800 | 86840 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE LOCAL | CONST CONST | $1,177,600 $143,300 $263,900 | 2015 2015 | ODOT |
| Description: RESURFACING FROM RITTMAN SOUTH CORP LINE TO MEDINA COUNTY LINE | ||||
| SR 585 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| WAYNE | CHIPPEWA TWP | PRESERVATION | $603,500 | 88797 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| STP-S STATE | CONST CONST | $482,800 $120,700 | 2015 2015 | ODOT |
| Description: RESURFACING FROM 0.21 MILES SOUTH OF SR 57 TO SR 604 | ||||
| SR 585 | ||||
|---|---|---|---|---|
| County | Location | Class | Cost | PID |
| WAYNE | CHIPPEWA TWP | OPERATIONAL | $650,000 | 89529 |
| Funding | ||||
| Fund Type | Phase | Amount | Year | Sponsor |
| HSP STATE | CONST CONST | $643,500 $71,500 | 2012 2012 | ODOT |
| Description: CONSTRUCT OFFSET TURN LANES AND MODIFY SIGNAL AT GATES ST | ||||